  1. The number of carriageway defect or pothole reports received from members of the public.
Please see the table provided below for Q2.
  1. The number of those reports closed under each closure code or outcome category used by the council (for example, but not exhaustive, "Inspection Complete, No Further Action" or equivalent), broken down by closure code.
    Please see the below table, this is just for any customer reports with a subject of Carriageway Pothole or Carriageway Damage. As this is selected by the requestor, not every report is necessarily related to a highway defect.
Outcome2023/242024/252025/26Grand Total
Cancelled - New Inspection Raised (System Use Only)404029109
Closed - in Future Programme7665401371443
Closed - Not Highways - Other NCC46121876
Enquiry Received4047437524
Forwarded to Incident Response 145
Further Drainage Work Required1  1
Holding Response Sent851932
Insp Comp - Investigate Further141318
Insp Comp - No Further Action902491251323531384
Inspection - Wet Weather  11
Inspection Complete1122841
Inspection Required3126
Insurance Claim Form Sent2 13
Insurance Claim in Progress51 6
Passed To Supply Company (DNO) 2 2
Resolved no action as not NCC262281391934
Section 81 - Utilities notified15512367345
Veh Access - Awaiting Customer Response49  49
Work Complete20592136053683371030
Works Ordered298172311484852
(blank)1449
Grand Total339872451652367110870
 
  1. The number of pothole or carriageway defect repairs carried out, broken down into temporary and permanent repairs. If this split is not recorded, please state that it is not recorded. – This is not recorded.
  2. The number of carriageway locations that were repaired more than once within any 12-month period. – This is not recorded, all defects are recorded as individual defects.