Dear ***** *****
FREEDOM OF INFORMATION ACT 2000 – REQUEST FOR INFORMATION REFERENCE FOI/4952
Thank you for your request for information relating to shared use routes, which we have dealt with under the Environmental Information Regulations 2004.
According to the Department of Transport definition "Shared Use Routes" are designed to accommodate the movement of pedestrians and cyclists. They can be created from new, or by converting existing footways or footpaths. Shared Use Routes may be segregated or unsegregated." These will include footways, footpaths, towpaths or any other public right of way in the area. Please include all of the above when counting.
1. Where possible, the amount of miles of Shared Use Routes in existence in your local authority area on 28/10/2024.
At present, there are approximately 150.5 miles of shared use routes adjacent to carriageway. There are also 1,773 miles of Right of Ways across the county. This includes bridleways, byway open to all traffic (BOAT), restricted byways and footpaths.
2. Where possible, the amount of miles of pedestrian footways, footpaths, towpaths or any other public right of way in the area that have been converted to Shared Use Routes in the past 6 years. Please provide a breakdown for each calendar year. This time period should include (01/01/2018-01/01/2023) and where possible (01/01/2024-28/10/2024).
9,268 metres of footways (non-public right of way footpaths, bridleways etc.) have been converted to shared use routes in the last 6 financial years.
Infrastructure delivered was historically categorised based on funding reporting requirements. Therefore for the period 2018/19 to 2019/20, this is categorised as ‘Off-road segregated (any cycle paths not on-road, including shared use next to the carriageway and away from roads)’ – in 2018/19 there were 6,057 metres delivered, and in 2019/20 there were 2,986 metres delivered. From 2020/21, this is recorded differently and during the period 2022/23 there were 225 metres of shared use (walking and cycling) facilities delivered, with none delivered in 2020/21, 2021/22 or 2023/24.
Infrastructure delivered was historically categorised based on funding reporting requirements. Therefore for the period 2018/19 to 2019/20, this is categorised as ‘Off-road segregated (any cycle paths not on-road, including shared use next to the carriageway and away from roads)’ – in 2018/19 there were 6,057 metres delivered, and in 2019/20 there were 2,986 metres delivered. From 2020/21, this is recorded differently and during the period 2022/23 there were 225 metres of shared use (walking and cycling) facilities delivered, with none delivered in 2020/21, 2021/22 or 2023/24.
As the construction of some schemes will span more than one financial year, the figures given above are based on the financial year in which schemes were completed.
3. Where possible, could you provide the specific number of miles of pedestrian footways that have been converted to Shared Use Routes in the past 6 years. Please provide a breakdown for each calendar year. This time period should include (01/01/2018-01/01/2023) and where possible (01/01/2024-28/10/2024).
225 metres of footway (note, this figure excludes footpaths, towpaths or any other public right of way). This figure relates to schemes delivered in 2022/23 financial year.
4. Where possible, could you provide the specific number of miles of pedestrian footpaths converted to Shared Use Routes in the past 6 years. Please provide a breakdown for each calendar year. This time period should include (01/01/2018-01/01/2023) and where possible (01/01/2024-28/10/2024).
Unfortunately we do not hold this information and we are therefore unable to provide anything in response to this question.
We trust this now satisfies your request and that you find this information to be helpful.
If you are dissatisfied with the handling of your request, you have the right to ask for an internal review. Requests should be submitted within 40 working days of the date of receipt of the response to your original request and should be addressed to: Complaints and Information Team, Nottinghamshire County Council, County Hall, Loughborough Road, West Bridgford, NOTTINGHAM, NG2 7QP or [email protected]
If you are not content with the outcome of the internal review, you have the right to apply directly to the Information Commissioner for a decision. The Information Commissioner can be contacted at: Information Commissioner’s Office, Wycliffe House, Water Lane, WILMSLOW, SK9 5AF or https://ico.org.uk/make-a-complaint/foi-and-eir-complaints/
Please remember to quote the reference number above in any future communications.
Your privacy: we use your personal information such as name and address so that we can comply with our legal obligations to respond to FOI requests. For further details about the use of information about you, please see the information handling privacy notice on our website at https://www.nottinghamshire.gov.uk/media/4323566/informationgovernanceandinformationrightsprivacynotice.pdf
Yours sincerely
Complaints and Information Team
Chief Executives Department
Nottinghamshire County Council
The Council is committed to protecting your privacy and ensuring all personal information is kept confidential and safe. For more details see our general and service specific privacy notices at: https://www.nottinghamshire.gov.uk/global-content/privacy